A rock collapse at the Tarbela Dam T-5 project on Monday sent water rushing into tunnels and an unfinished power house. Work on the 1,530MW hydropower extension was halted and all workers were moved to safety. The Water and Power Development Authority (Wapda) said no one was killed or injured, as of 3 AM PKT on 10 November.
Wapda has rejected reports that the main T-5 tunnel collapsed. It says the key structures were not damaged. However, district officials said damage was still being assessed, and a high-level inquiry has been ordered.
What happened at Tarbela Dam T-5
The incident took place on 9 November at the Tarbela 5th Extension Hydropower Project site in Swabi. According to Wapda, a “weak rock mass” gave way while crews were digging the second bench of a connecting tunnel. As a result, water from the project’s intake pit flowed into the tunnel. It then reached the power house, which is still under construction.
Wapda declared an emergency and stopped construction. Pakistani and foreign staff were taken to a safe location, The Express Tribune reported. Rescue teams pulled out one Pakistani worker who had been carried away by the water, according to the newspaper and Business Recorder.
Local accounts differ slightly on the cause. Aaj News, quoted by Business Recorder, reported a crack in a protective embankment. Haripur Deputy Commissioner Waseem Ahmed also said water entered after a bund gave way. Wapda, by contrast, describes the event as a rock fall inside the excavation area.
Wapda says main structures are safe
In its statement, Wapda said the intake pit had been fully drained. No more water was entering the downstream work sites, it added. Pumping water out of the power house has begun.
Wapda called reports of a T-5 tunnel collapse “incorrect”. It said the main tunnel, the power house, the tailrace culvert and the switchyard were not damaged. Dawn reported that senior Wapda staff, the contractor and the project engineer were still checking the site.
Ahmed said the next steps would depend on the inquiry. “The next course of action would be determined after the investigation report was received,” he told The Express Tribune. The inquiry will examine whether a structural weakness or a technical fault caused the incident.
Safety advice for people along the Indus
A senior district official told Dawn there was no current risk of flooding downstream of Tarbela. Even so, the dam released extra water for what officials called “unavoidable” reasons. This is expected to raise water levels in the Indus River.
Swabi Deputy Commissioner Nasarullah Khan urged people to avoid bathing, swimming and boating in the river. He also asked residents to ignore rumours and follow official notices only.
A troubled project
The T-5 project will add three 510MW units to Tarbela. When finished, it will lift Tarbela’s total capacity to 6,418MW, up from 4,888MW today. Business Recorder put its expected average output at 1.347 billion units yearly.
The scheme carries an approved price tag of $807 million. Of this, $390 million comes from the World Bank, while the Asian Infrastructure Investment Bank is lending $300 million. Power Construction Corporation of China won the $354.6 million civil works contract in May 2021.
However, the scheme has faced repeated delays. In 2024, officials blamed slow clearance from the Indus River System Authority (IRSA) to close the tunnel. In August 2025, rising reservoir levels flooded the site and work stopped for a time. Later, a government inquiry into a cofferdam collapse held the contractor, the consultant and Wapda responsible, Dawn reported.
Reports differ on the current completion date. Business Recorder and The Express Tribune cite September 2027, while Dawn reported a revised target of June 2028. Either way, Monday’s incident could push the timeline back further.
Why Tarbela Dam T-5 matters
Tarbela is one of the world’s largest earth-filled dams and a key source of cheap hydropower for Pakistan. The extension is meant to add clean electricity without building a new dam. For that reason, further delays could affect power supply plans and costs.
For now, construction remains suspended. The inquiry’s findings will decide when work can safely resume.