Puerto Rico Supreme Court Ends Luma Energy Contract in 5-4 Ruling

Supreme Court of Puerto Rico in San Juan, which ruled the government can end the Luma Energy contract

Puerto Rico’s Supreme Court has ruled that the government can end its contract with Luma Energy, the private company that runs the island’s power grid. The court made its narrow 5-4 decision public on Wednesday, 25 November 2026. It sets out a one-year transition period before the Luma Energy contract ends.

The ruling is a major win for Governor Jenniffer González. She promised during her election campaign to cancel the deal. However, it also leaves the US territory facing an uncertain year, with no successor company yet named.

Why the Luma Energy contract became so divisive

Luma took over the transmission and distribution of electricity in Puerto Rico in June 2021. The company is a consortium of Canada’s Atco and Houston-based Quanta Services.

It inherited a grid that was badly damaged. Hurricane Maria wrecked much of the island’s power network in 2017. Before that, the state-owned Puerto Rico Electric Power Authority (PREPA) had suffered decades of neglect and mismanagement.

Even so, frequent outages continued under Luma. As a result, many Puerto Ricans protested for years over the cost and quality of service. A separate private firm, Genera PR, runs power generation, and it has also been blamed for some of the blackouts.

The government sued Luma nearly a year ago. Governor González has accused the company of “constant interruptions” and “unnecessary outages”. She has also blamed it for pushing electricity prices to record highs.

Funding is a key part of her case. In December 2025, González said Luma had nearly $11 billion in federal money available to rebuild the grid. Yet, she said, it had recovered only about $550 million in reimbursements from the Federal Emergency Management Agency (FEMA).

A legal fight over an extension

The dispute centres on how Luma’s contracts were extended. The government has two main deals with the company. One covers operation and maintenance. The other is a supplemental agreement, needed because PREPA is still stuck in debt restructuring.

Both deals were due to expire in November 2022. However, the government extended the supplemental agreement with a letter. González has argued that this letter gave Luma indefinite control. She said it broke the law and the principles of sound public administration.

Split court and claims of pressure

The close vote has exposed deep divisions on the bench. Judge Ángel Colón Pérez, who voted against cancellation, said the ruling came from “an excessive eagerness to satisfy a capricious request” from the leader in power. That appeared to be a reference to the governor.

In response, Judge Roberto Feliberti Cintrón, who sided with the majority, sharply rejected the claim. “We do not bow to external pressures,” he wrote.

Luma has called for an “immediate, rigorous, and transparent investigation” into the claims that judges were pressured. The company said it disagrees with the decision but will respect the legal process. It added that it is “carefully evaluating all available legal alternatives”.

What happens to Puerto Rico’s power now

González said her administration will seek a new operator within the one-year window. She also said transmission and distribution will not return to PREPA. “There will be no chaos,” she said.

Nevertheless, the federal oversight board that controls the island’s finances has raised concerns. It said ending the contract “creates enormous uncertainty” at a time when residents and businesses want stability. The board noted there is no clear plan or successor company in place.

For the island’s 3 million-plus residents, the main worry is simple: whether the lights stay on. Crews are still repairing the grid nearly a decade after Maria. Therefore, any handover must avoid disrupting that work and the flow of federal funds.

The coming months will show whether a new operator can be found quickly. Luma could also seek further legal options, which may delay the transition. For more stories from the region, visit our Latin America section. Earlier, we reported on a $2 billion resort project in Cabo Rojo.